IIQ certification query

Which IIQ version are you inquiring about?

[IIQ 8.4p2]

Share all details about your problem, including any error messages you may have received.

*Hi everyone,

We have a certification which is configured to escalate and the certification item was completed by the certifier well before the escalation date. But still, the certification item was escalated to a new owner. The certification workitem is still open. But when we view the workitem, it shows that it is signed .

The certification item shows that its in end phase currently. But the workitem was not archived after it was signed.

Any suggestions or directions to look for?*

can you checkl below things:

  • Item status at escalation time: Check whether the item was actually in a completed state, or still showed as delegated, returned, or open when the escalation ran.
  • Certification history and audit logs: Compare the timestamps of the item completion, the sign-off, and the escalation to see the real sequence.
  • Refresh or maintenance tasks: A refresh can reopen or change items, and the Perform Maintenance task is what handles escalation and finishes or archives work items. Check that it ran after the sign-off and look at its logs for errors.
  • End phase with pending actions: A certification stays in End phase while remediations or other follow-up actions are pending. That can leave the work item open even though it’s signed.
  • Escalation configuration: Check the escalation rule and settings for how they pick items and whether they account for items that are already completed.

Hi @haluchi

As @naveenkumar3 said, I would suggest checking the following:

1. Verify the certification item status before the escalation was triggered. Confirm whether it was already marked as completed.

2. Check the certification history and audit logs to compare the completion, sign-off, and escalation timestamps.

3. Review the Perform Maintenance task logs to see whether it ran successfully after the work item was signed.

4. Check the escalation rule and configuration to ensure completed items are excluded from further escalation.

5. Verify whether any pending remediation actions are preventing the work item from being archived.

One thing I would particularly investigate is why the escalation process picked up an item that was already signed.

Also check the escalation handled through the standard IIQ configuration or a custom rule?

Hi @haluchi ,

Kindly go through below link.

Thank you,

Harikrishna

Do we know what causes this issue?

Also, I don’t see access review workitems going to archive. Is it a setting some place to do that?