IIQ 8.3 → 8.5 Upgrade: Is the 9.0 Pre-Check Worth Running Early?

Which IIQ version are you inquiring about?

8.3

Please share any images or screenshots, if relevant.

[Please insert images here, otherwise delete this section]

Please share any other relevant files that may be required (for example, logs).

[Please insert files here, otherwise delete this section]

Share all details about your problem, including any error messages you may have received.

Hi everyone,

We’re starting to plan an IdentityIQ 8.3 → 8.5 upgrade in a fairly mature environment with a healthy amount of customizations, integrations, workflows, and the usual collection of things that seemed like excellent ideas at the time.

One question I’m particularly interested in:

Has anyone used the IdentityIQ 9.0 Pre-Check utility before beginning an 8.5 upgrade?

I understand the tool is intended for 9.0 readiness and Jakarta migration planning, but I’m wondering if anyone found value in running it earlier to:

  • Identify customization debt
  • Inventory custom code and plugins
  • Find javax.* dependencies
  • Discover obsolete UI components or configuration patterns
  • Highlight areas that should be cleaned up before upgrading to 8.5

Did it provide useful insight during upgrade planning, or does it really only become valuable once you’ve landed on 8.5?

I’m also looking for lessons learned on a few other areas:

  • What cleanup activities delivered the biggest payoff before upgrading?
  • Any tools, scripts, or reporting approaches you used to inventory rules, workflows, plugins, custom connectors, JARs, or modified SailPoint objects?
  • Any unexpected issues with connectors, IQService, TLS, database upgrades, performance, or custom code?
  • What were your “must-have” Go/No-Go tests before production cutover?
  • If you could do the upgrade over again, what would you tackle earlier?

Our current thinking is:

Inventory → Cleanup → Rehearse 8.3 → 8.4 → 8.5 → Stabilize → Run 9.0 Pre-Check and build a remediation backlog.

I’d appreciate any advice, lessons learned, tooling recommendations, or things you wish someone had told you before starting.

Thanks in advance.

Welcome to the community, Hilary.

I would keep the 9.0 Pre-Check in the plan, but not run it against 8.3. SailPoint supports iiq-precheck on 8.5 and 9.0 only. Once you have an 8.5 rehearsal environment, run it there. It can identify javax.* dependencies and other customizations that need attention for 9.0.

Before upgrading, I would inventory Rules, Workflows, TaskDefinitions and Applications using export -clean, run plugin list, and inventory custom JARs and filesystem changes.

For the 8.3 → 8.5 path, SailPoint documentation is inconsistent. The Upgrade Considerations page says versions can be skipped, while current SailPoint Customer Success Engineering guidance says every intermediate GA release should be installed, although interim patches can be skipped. I would therefore use 8.3 → 8.4 GA → 8.5 unless SailPoint Support confirms a direct 8.3 → 8.5 upgrade for your environment.

Before rehearsal, remove existing e-fixes, make sure IQService matches the IIQ version and patch level, and back up your customizations and filesystem changes.

For Go/No-Go, I would test the critical business paths: aggregation, provisioning, lifecycle events, access requests/approvals, certifications, scheduled tasks, IQService, plugins, and critical integrations.

I would use:

Inventory → Cleanup → Rehearse 8.3 → 8.4 GA → 8.5 → Stabilize → Run Pre-Check → Build 9.0 remediation backlog.

I don’t think we can skip 8.4 in the process. I confirmed this with Sailpoint ES, they told us that there is no change in the upgrade path. You need to go from 8.3 to 8.4 to 8.5.

Thanks, @neel193. The docs are a bit inconsistent here, and since you have already confirmed it with SailPoint, I would go with 8.3 → 8.4 GA → 8.5 as well. Appreciate you pointing it out.